Opportunity 40: Transition from 2 to 1 turbine on Ringhorne | |
---|---|
Several measures have been implemented to reduce the power requirement on board, and thus be able to go from 2 to 1 turbine. Measure implemented: Installation of a "Solar forward purge air system", change of pigtails, tuning of fuel gas valves and reduction of vibrations in fuel manifold. Estimated annual results:
|
|
System group: System general | |
Type: Operations optimisation | Investment: Not quantified |
Profitability: 13 MNOK/year | Implementation: Implemented |