| Opportunity 37: Bleeding of gas during maintenance | |
|---|---|
|
Engie wanted to reduce emissions of hydrocarbon gas to air and avoid exposure to personnel. Solution to achieve this: installing a high pressure connection for using HT hose to e.g. the HP flare system. The gas goes to the HP flare thereafter to the 1st train re-compressor and then back to the process. Estimated yearly results:
|
|
| System group: Main process (20-29) | |
| Type: Modification | Investment: < 0,1 MNOK |
| Profitability: Profitable | Implementation: Implemented |