Opportunity 36: Electrification of a Jack-up drilling rig | |
---|---|
Aker BP has contracted Maersk Drilling for a XLE4 rig. The rig has the possibility for electric power supplied from Valhall, in addition to regular diesel generators when electric power is not available. The rig is contracted for five years, with an option for five times one-year in addition, for P&A activities at the Valhall field. Drivers for this solution are available power from Valhall, high emissions and costs related to diesel consumption, lower noise levels and better working conditions (previously the drilling rigs have been closed down during windless conditions due to excessive concentration of air pollution over the rig). Estimated annual results:
|
|
System group: Main process (20-29) | |
Type: Modification | Investment: >50 MNOK |
Profitability: Profitable | Implementation: Implemented |